Here are the major scheduled road and lane closures for Monterey County from Sunday, June 7 through Sunday, June 14, 2015. Please keep in mind that construction work is weather-dependent.
Highway 1 – Salmon Creek: June 9 – June 10
- Daytime drainage work along Highway 1 at Salmon Creek from 7 a.m. to 3:30 p.m.
- Motorists should expect delays of approximately 10 minutes.
Highway 1 – South Coast: June 9 – June 12
- Daytime drainage work along Highway 1 between the Big Creek Bridge and the Vincente Creek Bridge from 7:30 a.m. to 4 p.m.
- Motorists should expect delays of approximately 10 minutes.
PG&E Gas Line Replacement Project – Highway 68: June 7 – June 13
- Gas line replacement work will result in night time lane closures along eastbound and westbound Highway 68 between Olmsted Road and Toro Road from 8 p.m. to 5 a.m.
- Motorists can expect delays of approximately 15 minutes
Highway 101 – San Lucas: June 11 – June 12
- Daytime sweeping along northbound and southbound Highway 101 between Route 198 and Lockwood/San Lucas Road from 8 a.m. to 3 p.m..
- Motorists should expect delays of approximately 10 minutes.
Highway 101 – King City: June 9 – June 10
- Daytime sweeping along northbound and southbound Highway 101 between Broadway and Jolon Road from 8 a.m. to 3 p.m.
- Motorists should expect delays of approximately 10 minutes.
Highway 101 – Greenfield: June 7 – June 12
- Daytime and night time pavement work along northbound and southbound Highway 101 at Espinosa Road.
- Motorists should expect delays of approximately 10 minutes.
Highway 101 – San Juan Road Interchange Project: June 7 – June 12
- Night time construction work along southbound and northbound Highway 101 between Dunbarton Road (South) and Cannon Road/Rocks Road from 7:30 p.m. and 5:30 a.m.
- The southbound and northbound San Juan Road Interchange ramps will be subject to closure.
- Motorists should expect delays of approximately 10 minutes.
Highway 183 – Salinas to Castroville: June 9
- Daytime chip seal work along Highway 183 between San Jon Road and the Espinosa Slough Bridge from 6 a.m. and 6 p.m.
- Traffic control consists of one-way reversing traffic control with flagging
- Motorists should expect delays of approximately 15 minutes.
South Salinas: Westbound Blanco Road Closure
- Industrial wastewater pipe installation will result in the all-day closure of westbound Blanco Road between Blanco Circle and La Mesa Way.
- Eastbound Blanco Road will be subject to daytime lane closures from 7 a.m. to 4 p.m.
- Detour signs will be in place to help direct motorists.
- Motorists should expect delays of approximately 15 minutes.